PHASE 2 PROJECT PHOTOS – CONSTRUCTION PHOTOS

Gravel for Stair -5 pit Facing North (800x600).jpg Installed metal decking at Steel arch Facing East (800x600).jpg Placing 3-4 gravel insde Stair -5 pit Facing West (800x600).jpg Started installing rebar mats at Elev. 1,2,3 (3rd Floor) Facing South-West (800x600).jpg Started installing the shear wall panels at Elev. 5,6 (3rd Floor) Facing East (800x600).jpg Underground roughing for sanitary sewer by Elev. 1,2,3 Facing South (800x600).jpg Underground storm piping along column line 2.5 Facing South-East (800x600).jpg Backfilling underground roughing along column line 2.5 between G-K Facing East (800x600).jpg Electricicans working on the underground piping by the bridge Facing Cherry Street (800x600).jpg
Previous pageNext page Started installing the shear wall panels at Elev. 5,6 (3rd Floor) Facing East (800x600)
Started installing the shear wall panels at Elev. 5,6 (3rd Floor) Facing East (800x600)